basics:affordability:economic_feasibility_of_passive_house_design
Differences
This shows you the differences between two versions of the page.
Both sides previous revisionPrevious revisionNext revision | Previous revision | ||
basics:affordability:economic_feasibility_of_passive_house_design [2015/07/01 11:11] – [3Cost effective deep energy renovation] kdreimane | basics:affordability:economic_feasibility_of_passive_house_design [2019/02/28 09:45] (current) – cblagojevic | ||
---|---|---|---|
Line 13: | Line 13: | ||
The energy-cost savings then can be used to finance the extra investment cost which are probably needed to get better building components to form the energy efficient building envelope: | The energy-cost savings then can be used to finance the extra investment cost which are probably needed to get better building components to form the energy efficient building envelope: | ||
* more and better thermal insulation layer | * more and better thermal insulation layer | ||
+ | |||
* windows with low U-value < 0.85 W/m²K | * windows with low U-value < 0.85 W/m²K | ||
+ | |||
* ventilation system with heat recovery | * ventilation system with heat recovery | ||
+ | |||
* … | * … | ||
To compare energy cost savings with extra investment costs both cost categories have to be re-calculated via dynamic finance calculation methods: annual expenses must be transformed to present cash value or vice versa. | To compare energy cost savings with extra investment costs both cost categories have to be re-calculated via dynamic finance calculation methods: annual expenses must be transformed to present cash value or vice versa. | ||
Line 52: | Line 55: | ||
The costs coming out of the invoicing are sorted by components and energy saving actions, see figure 3, such as: | The costs coming out of the invoicing are sorted by components and energy saving actions, see figure 3, such as: | ||
* air tightness | * air tightness | ||
+ | |||
* thermal insulation of cellar, bottom slab, outside wall, roof | * thermal insulation of cellar, bottom slab, outside wall, roof | ||
+ | |||
* windows, entrance door, shading | * windows, entrance door, shading | ||
+ | |||
* heating system | * heating system | ||
+ | |||
* ventilation system | * ventilation system | ||
To compare the costs of several components specific cost values in €/m² were calculated. The area used is the same treated floor area, which is used in PHPP to do energy balance calculations. So cost data for investment and energy consumption can easily and directly be compared. | To compare the costs of several components specific cost values in €/m² were calculated. The area used is the same treated floor area, which is used in PHPP to do energy balance calculations. So cost data for investment and energy consumption can easily and directly be compared. | ||
Line 73: | Line 80: | ||
PH components as described above are economically reasonable with present boundary conditions, see table 4. So the higher investment costs are paid back by reduced energy consumption costs during lifetime of the building. Therefore the documentation of 'total lifecycle costs' is important to give a transparent view of the facts. | PH components as described above are economically reasonable with present boundary conditions, see table 4. So the higher investment costs are paid back by reduced energy consumption costs during lifetime of the building. Therefore the documentation of 'total lifecycle costs' is important to give a transparent view of the facts. | ||
Two effects have to be pointed out here: | Two effects have to be pointed out here: | ||
- | * Unordered List Itemit | + | * it is worth while to optimize all components to the cost optimum. Having rather high energy prices this intends to reduce energy costs and have some more investments in corresponding energy saving components. |
- | * Unordered List ItemThe | + | |
- | * Unordered List ItemWindows | + | * The numbers of cost data out of the study shown in this section are by intention taken from a 'cost effective' |
- | * Unordered List ItemVentilation | + | |
+ | * Windows | ||
+ | |||
+ | * Ventilation | ||
Using all the above mentioned numbers and calculating present values from all cost categories results in the total costs for PH and LEB shown in figure 3. | Using all the above mentioned numbers and calculating present values from all cost categories results in the total costs for PH and LEB shown in figure 3. | ||
Summary and outlook: Lower interest rates get the capital cost reduced and higher energy prices will lead to higher savings. So the present situation favors investment in energy efficiency components for buildings. | Summary and outlook: Lower interest rates get the capital cost reduced and higher energy prices will lead to higher savings. So the present situation favors investment in energy efficiency components for buildings. | ||
Line 90: | Line 101: | ||
| price for electricity *) | **0.22 €/kWh** | final energy| | | price for electricity *) | **0.22 €/kWh** | final energy| | ||
**Table 2: ****Basic assumptions for dynamical cost calculation for row house 2008. | **Table 2: ****Basic assumptions for dynamical cost calculation for row house 2008. | ||
- | Siehe dazu auch [Kah/Feist 2008] (*) Energy price and interest rate in 2008.** | + | Also see [Kah/Feist 2008] (*) Energy price and interest rate in 2008.** |
\\ | \\ | ||
Line 124: | Line 135: | ||
- | + | [{{ :picopen:school_building_figure_6.png?700 |**Figure 6:** **School building – renovation with PH-components – variant No 6 was realized. | |
- | [{{ :picopen:school_building_renovation_with_ph-components_.png?nolink | + | |
Detailed investment costs for energy saving actions in addition with basic ' | Detailed investment costs for energy saving actions in addition with basic ' | ||
+ | |||
\\ | \\ | ||
- | [{{ :picopen:school_building_renovation_with_ph-components_variant_no_6_was_realized..png?nolink | + | [{{ :picopen:renovation_with_ph_comp.png?700 | **Figure 7:** **School building – renovation with PH-components – variant No 6 was realized. |
Full life cycle costs as present cash value for 33 years. This time span is assumed as an average life time for all components. | Full life cycle costs as present cash value for 33 years. This time span is assumed as an average life time for all components. | ||
The analysis shows clearly: the cost optimized variants No 5 (EnEV, german building code) and No 7 (PH) are equal within the accuracy of the calculations, | The analysis shows clearly: the cost optimized variants No 5 (EnEV, german building code) and No 7 (PH) are equal within the accuracy of the calculations, | ||
Line 155: | Line 166: | ||
Acknowledgements: | Acknowledgements: | ||
* IEA Task37 " | * IEA Task37 " | ||
+ | |||
* IEA Annex 61 " | * IEA Annex 61 " | ||
+ | |||
* Deutsche Bundesstiftung Umwelt | * Deutsche Bundesstiftung Umwelt | ||
+ | |||
+ | |||
+ | |||
+ | \\ \\ \\ \\ \\ | ||
+ | |//The sole responsibility for the content of Passipedia lies with the authors. \\ While certain marked articles have been created with the support of the EU, they do not necessarily reflect the opinion of the European Union; \\ Neither the EACI nor the European Commission are responsible for any use that may be made of the information contained therein.//| \\ | ||
+ | \\ | ||
+ | |||
basics/affordability/economic_feasibility_of_passive_house_design.1435741879.txt.gz · Last modified: 2015/07/01 11:11 by kdreimane